You have booked leave in Dubai so you can collect the keys to your flat in India. A week before the flight, the builder invites you to a “fit-out inspection”. The email says the permanent electricity connection is pending and asks you to sign that possession has been delivered.

Before rearranging your trip, ask the builder one question in writing: What exactly will they hand over, and which document will they expect you to sign?

Quick answer

Check the possession date in your agreement for sale, the registration for your project phase and the terms of any extension. If section 18 of India’s real estate law applies, a buyer can seek a refund with prescribed interest on withdrawing, or monthly delay interest while waiting for possession. Decide which outcome you want before signing a revised handover or settlement letter.

Reconstruct the promised handover

1. Read the clause for your unit

Find the signed agreement for sale, the possession clause and any grace period. Check what starts the period and what conditions attach to it.

Put any later document you signed beside the original. Keep the booking form and brochure as evidence of representations, but identify which date comes from which document.

2. Check the registered project and phase

Use the Ministry of Housing and Urban Affairs’ directory of RERA authorities to find the regulator for the Indian state or territory where the project stands.

Search by registration number, promoter name and phase. Two towers advertised under one brand can have different registrations.

Save the dated project entry, completion disclosures and any extension order that actually covers your phase.

3. Reconcile your payments

Match the builder’s demands with bank transfers, home-loan disbursements and receipts. Note any instalment the builder says is late.

If the lender paid directly, obtain its disbursement statement. Compare rupee amounts received with the builder’s ledger so currency conversion or transfer fees do not look like a missing instalment.

When the agreement, the portal and the sales office give different dates

Imagine that the agreement names 30 June as the possession date. The portal gives 31 December as the revised project completion date. In September, an email invites buyers to visit their flats.

These are three dates for three events. The first comes from the buyer’s contract. The second concerns the registration of a particular project or phase. The third records an invitation whose meaning depends on its wording and what the builder could deliver that day.

Ask the promoter for the order behind the December date, including the registration number and the period covered. Compare it with the clause that sets the date for your own unit.

If the clause refers to a grace period, check whether it runs automatically or only when specified circumstances arise. If the promoter relies on a public authority’s decision, ask for the document and its connection to the work outstanding in your phase.

The Housing Ministry’s RERA FAQs explain a buyer’s right under section 19 to specified project information, including the stage-wise schedule of completion.

Use that right to ask a precise question. “Which approval remains outstanding for occupation of Tower B, and when did you apply for it?” is easier to check than “Will the flat be ready soon?”

Keep the response even if the promised date subsequently moves again.

Decide whether you want the flat or your money back

Under section 18(1) of the Real Estate (Regulation and Development) Act, 2016, failure to complete or give possession as agreed can entitle an allottee who withdraws to seek return of the amount received with prescribed interest. Compensation may also be claimed as provided by the Act.

A buyer who stays in the project can seek interest for each month of qualifying delay until handover. Coverage, the agreement and the facts matter.

If you want to move your parents into the flat, ask for a documented handover timetable and an assessment of delay interest.

If your priority is to exit, identify the sums paid to the promoter, including lender disbursements, before making a refund demand.

Where a bank financed the unit, read the loan and tripartite agreements to see how any refund would be applied. Keep the lender informed before changing payments.

How to compare a refund offer with continued ownership

A promoter may offer to return the booking amount now and the balance after it resells the unit. That is a proposed payment schedule. It has a different practical value from an immediate refund.

Read the trigger for each instalment, the date on which you must surrender your rights in the unit, what happens if the next buyer never appears and whether signing settles accrued interest.

Where the money went through a lending bank, find out which amount would actually reach you after the loan is closed.

If the builder offers a credit against the final demand instead, ask for the calculation in rupees. A credit of ₹2 lakh is difficult to assess without knowing the amount on which interest was calculated, the period covered and the date up to which you would release claims.

Put stamp duty, loan interest, statutory delay interest and any separate claim for loss on different lines. Each has a different basis. Counsel can then identify the items the offer includes and the items it leaves open.

Consider what the choice costs your family in practice. If you keep the flat, can your parents remain in their rented home through another monsoon? If you leave, do you need the loan discharged before another lender will fund a replacement?

These questions do not determine the legal entitlement, but they can decide whether a settlement is worth accepting.

What if the builder offers keys or a new date?

Read what you are being asked to accept. Permission to inspect a flat, access for interior work and a formal offer of possession can be three different events.

Ask for the written offer, the applicable occupancy or completion approval covering your building, the payment statement and the proposed handover form. Record missing services or defects and the date you inspected.

A revised date on the regulator’s portal deserves investigation. Obtain the extension order and read its basis, period and scope with the contractual possession clause.

If the builder asks you to sign a waiver of delay interest, identify the amount and period you would give up in exchange for the offer. Have counsel review the document before accepting or rejecting possession.

A useful inspection record identifies the building, floor, unit, date, people present and purpose of the visit. Photograph missing fittings and any access problems with enough context to identify the room or approach road.

If your family member signs an attendance sheet, ask them to obtain the complete page. A signature under the words “received possession in full satisfaction” raises a different issue from a signature confirming that they attended a site visit.

Separate your response to the physical condition from your response to the legal offer. You might be willing to inspect on Saturday and still need the occupancy document and statement of dues before you can answer the handover proposal.

Put those two points in the same email and ask for a reply by the promoter’s stated deadline. Silence leaves the builder’s email as the only written account of what it offered.

Where to take a complaint

Section 31 permits an aggrieved person to complain about a breach of the Act, rules or regulations to the authority or adjudicating officer, as applicable.

The Supreme Court’s judgment on RERA refund, interest and compensation jurisdiction explains the division of functions. The authority can determine refund and interest claims under section 18. The adjudicating officer decides statutory compensation within their remit.

Name the relief you are asking for and explain the figures behind it.

If the project cannot be found, check the exact promoter entity, phase and registration requirements before choosing a complaint route.

If insolvency proceedings have started, tell counsel immediately and send the public notice. A formal insolvency process can change where and when a buyer must act.

Write the complaint so a stranger can follow the money

Start with your unit and the legal name of the promoter on the agreement. Then give the agreed date, what happened when that date passed and the exact outcome you seek.

A short schedule that ties each payment to its demand and receipt helps the reader verify a refund figure. Put contested amounts in a separate column and explain why they are disputed. If part of the purchase price is still unpaid, show it.

For a delay-interest claim, identify the period for which you say interest runs and why you selected its end date.

A builder who says a valid handover occurred earlier may rely on a letter you received months ago. Include it, alongside the approval status and your reply.

Addressing that disagreement at the start is more persuasive than submitting a long chain of unanswered reminders.

If discussions produce a settlement, read the enforcement and payment terms before withdrawing a pending complaint. Ask counsel how the settlement will be recorded and what happens if the promoter pays the first instalment and misses the second.

A settlement date matters most when there is a clear consequence for missing it.

Prepare a file you can use from the UAE

  • The agreement and relevant annexures, with the possession clause marked.

  • Your phase registration, any extension orders, and dated progress or completion records.

  • A payment ledger and the demands, receipts and bank entries supporting each line.

  • The latest offer, your replies and a copy of any waiver awaiting signature.

  • A one-sentence instruction stating whether you want possession or a refund.

If someone in India inspects for you, specify whether they can only photograph and report or can also accept keys and sign.

Give your representative a list of documents to request. Keep settlement authority separate if you want to approve the financial terms yourself.

Frequently asked questions

1. Is delay interest the same in every Indian state?

The applicable rules prescribe the rate. Ask for the rule, the dates and the amounts used in the calculation. Another buyer’s spreadsheet may concern a different state or payment schedule.

2. Can I stop paying the home-loan instalments?

A delay by the promoter does not automatically suspend the loan agreement. Ask the lender in writing about your obligations, disbursements and any agreed change before missing a payment.

3. Can I refuse a handover offered by email?

Examine the offer promptly. The contractual terms, approvals, state rules and facts affect whether it is a valid offer and what a refusal would mean. Keep the email and attachments with the date of receipt.

4. Does living in Dubai mean I must file there?

The Indian project’s location identifies the relevant Indian RERA authority. Check its current filing and representation procedures and whether attendance is required for a particular hearing.

5. Can I seek delay interest while still wanting the flat?

Where section 18 applies, a buyer who does not withdraw from the project can seek prescribed interest for each month of qualifying delay until possession is handed over. The relevant dates, payments and any disputed offer of possession require review.

6. Does a revised completion date on the RERA portal automatically settle my claim?

Do not assume that it does. Obtain the actual extension order and review its scope, conditions and effect alongside your agreement. A revised registration date alone does not explain how your individual claim should be assessed.

7. Is a fit-out inspection the same as taking possession?

Not necessarily. An inspection, permission to carry out interiors and a formal handover may have different purposes and consequences. Read the invitation and proposed acknowledgment, and check the approval status before signing.

8. What is the difference between an occupancy certificate and a completion certificate?

An occupancy certificate concerns permission to occupy the building, including the relevant habitability and infrastructure requirements. A completion certificate concerns completion in accordance with the approved plans and specifications. Local terminology and approval arrangements can vary, so check which document applies to your building or phase. rera.mohua.gov.in

9. Can a family member inspect the property for me?

A family member may be able to inspect with the required authorisation and access arrangements. State clearly whether they may only inspect and report or may also accept keys and sign documents. Confirm any formal authority required before they act.

10. Should I sign a “full and final settlement” to collect the keys?

Review the document before signing. It may contain a release of delay interest or other claims. Identify what you receive, what you give up and whether the document accurately records the condition and approval status of the property.

11. What if the builder says my own payments were late?

Prepare a payment chronology showing demand dates, contractual due dates, transfers, lender disbursements and receipts. Identify any disputed demands. Your payment obligations and the promoter’s objections should be assessed alongside the delay claim.

12. Can I claim both delay interest and compensation?

They are distinct forms of relief, and the legal basis, supporting evidence and appropriate decision-maker need review. Do not assume that every expense or inconvenience will automatically be reimbursed. State each claimed amount separately and explain the loss it addresses.

13. What if the builder offers a refund only after reselling my flat?

Examine the proposal as a conditional payment arrangement. Check the payment deadline, what happens if resale does not occur, when you surrender your rights and whether interest continues. Review the consequences for any home loan before accepting.

14. What if my project is missing from the RERA portal?

Search using the exact promoter name, registration number and project phase. If it remains unlisted, check whether registration was required and which complaint route is available. Absence from a search result alone does not establish the project’s legal status.

15. Does a settlement promise mean I should withdraw my complaint immediately?

Review how the settlement will be recorded and enforced before withdrawing. Check payment dates, default consequences, lender arrangements and when any release of claims takes effect.